Come installare il condotto di ventilazione

Install Ventilation Duct
Install Ventilation Duct Ventilation duct mainly refers to the ventilation duct of central air conditioning system, which we often ignore it, but it is an important part of air conditioning system. It is a kind of metal or composite pipe for ventilation and air conditioning engineering of industrial and civil buildings. It is a municipal infrastructure to make the air circulate and reduce the concentration of harmful gases.
Classification of Usage
Divided into: supply and return air pipe of the purification system, ventilation pipe of central air conditioning, industrial supply, and exhaust air pipe, suction and exhaust air pipe of the environmental protection system, mine gas drainage pipe, mine rubber-coated cloth air duct, etc. Install Ventilation Duct
Classification of Shape
Diviso in: condotto tondo, rettangolare, condotto a spirale. Install Ventilation Duct
Classificazione della tecnologia di elaborazione
Divided into: angle iron flange duct, TDF flange duct. Install Ventilation Duct

Applicazione
The air duct is mainly used in industrial and construction engineering, and its application fields mainly involve: purification system of the dust-free workshop in electronic industry, purification system of the aseptic workshop for medicine and food, central air conditioning system of hotels, shopping malls, hospitals, factories and office buildings, exhaust duct for dust removal, smoke extraction and oil absorption in industrial pollution control, supply duct for the industrial environment or post comfort, air duct for air-conditioning, air-conditioning system for air-conditioning and air-conditioning Gas drainage system for coal mine gas drainage, air supply and return system for coal mine environment control, etc. Install Ventilation Duct
Costruzione del condotto dell'aria
- For more complex civil buildings, in the design stage, each type of work (HVAC, water supply and drainage, power supply and lighting, and Architecture) should first negotiate the space separation, and determine the elevation range of each kind of pipe. In general, they should not go beyond the limits set for themselves. In case of the crossing of individual pipe sections, it is necessary to negotiate with other projects. Install Ventilation Duct
- The principle to solve the collision and coordination of various ventilation pipes is generally: “small pipes give way to large pipes, and pressure gives way to no pressure”. For example, if the water pipe collides with the air pipe, the water pipe should be turned. If the cold and hot water pipes collide with the downpipe, the cold and hot water pipes should be changed. Install Ventilation Duct
- Before construction, the Engineer in charge of the main equipment shall draw the pipelines and single lines of each type of work on a plan. One-color pen for each type of pipe. Integrate the elevation of each intersection to see if there is any contradiction, find it in time, and solve the problem before installation. Install Ventilation Duct
- In order to reduce investment, save space and reduce floor height, some pipes without slope requirements can be laid through beams (such as water pipes, fire spray pipes, etc.). Install Ventilation Duct

Problemi comuni di installazione del condotto dell'aria
- Il materiale non soddisfa i requisiti di qualità
This kind of problem is a headache. If the material does not meet the requirements, the air duct will leak when the system is running, which will cause the loss of air conditioning load and affect the service life of the air duct. Install Ventilation Duct

- Rumore nel condotto
Questo fenomeno può essere causato dalla superficie irregolare, dallo spessore non uniforme, dall'evidente dentellatura, dalla fessura, dal foro di sabbia, dalla cicatrice e dalla corrosione della piastra, oppure dall'affondamento piano del condotto di ventilazione, dal lato sporgente verso l'esterno e dall'evidente deformazione.
- The warping angle, twist and elbow angle of ventilation duct are not accurate Install Ventilation Duct
This is due to the inaccurate setting out of plate cutting; The length and width of the sheet metal on the opposite side are not equal; The width of the undercut at the four corners of the ventilation duct is not equal; The setting position of bite seam is wrong, and the force of manual bite seam is different; Taking no corresponding reinforcement measures. In this case, the relative plane of the rectangular duct is not parallel, and the two ends are not parallel; The angle is not straight; The diagonals are not equal; Install Ventilation Duct
The bite is not tight. The final direct result is that the air duct connection is uneven, the installed air duct is not straight, the flange gasket is not tight, the system air leakage, resulting in air conditioning load loss, and shortens the service life. Install Ventilation Duct
Precauzioni per l'installazione del condotto dell'aria

1. Controllare la qualità dei materiali prima dell'installazione
Carefully measure the thickness of the steel plate. Before the installation of the air duct, the factory certificate and material quality certificate of the material must be checked first, and then the appearance of the material must be checked; Then measure the thickness of the steel plate. Prevent rework due to non-conforming materials. Install Ventilation Duct
2. La sicurezza del sollevamento dovrebbe essere garantita
The hoisting of the clean air duct is the same as that of the ordinary ventilation duct, and the suspender, cross arm, expansion bolt, and lower skid of the insulation air duct are required to meet the relevant specifications and quality acceptance standards. Install Ventilation Duct

3. Prestare attenzione a dispiegare i passaggi di soppressione
The construction personnel should strictly check the sheet metal, and control the length, width, and diagonal of each sheet metal within the allowable range; After blanking, the two sheets on the opposite side of the air duct should overlap to check the accuracy of the size; The reserved size of sheet bite must be correct to ensure the same width of bite; The biting seam sets at the four corners. When the biting seam is closed by hand, the center of both ends of the biting seam shall be tightened with a wooden hammer, and then the biting seam shall be uniformly compacted along the whole length. Install Ventilation Duct
4. Fai un buon lavoro di ispezione delle perdite di luce
After the ventilation duct assembles on the ground, the light leakage inspection should carry out before the heat preservation. According to the site conditions, the light leakage inspection can be carried out according to the internal or external light leakage, and the sealant shall be added at the light leakage, and the heat preservation can be carried out only when there is no light leakage. Install Ventilation Duct

5. Prova di perdita d'aria
For the supply and return air main pipe and branch pipe of purification system with higher grade, besides light leakage inspection, air leakage test shall be conducted after ground assembly. For the smaller system, it can be tested after the installation of the air duct, and for the larger system, it can be carried out after the segmented assembly on the ground as far as possible, so as to find problems and deal with them in time. Install Ventilation Duct
6. Il materiale del cuscino deve essere selezionato bene
The gasket at the flange connection of the ventilation duct shall be made of airtight, dust-free, elastic, and non-aging materials, such as closed cell sponge rubber plate, soft rubber plate, etc. the thickness of the gasket shall be 5-8mm. The joint shall be processed into ladder shape, and direct butt joint is strictly prohibited. Install Ventilation Duct
Può essere riassunto in una frase, come installare correttamente il condotto dell'aria è estremamente importante, quanto segue descrive alcune delle installazioni dei condotti dell'aria in passaggi dettagliati più completi, ridurre la perdita causata da problemi di installazione.
- Assicurarsi che i lavori di fondazione siano completati prima dell'installazione
The installation of the ventilation duct must be carried out after the completion of these foundation works; Before installation, the appearance quality shall be inspected, and the dust on the inner and outer surface and the debris in the pipe shall be removed. Install Ventilation Duct

● Condotto di ventilazione prefabbricato
Se non deve essere installato temporaneamente, non deve essere posizionato a piacimento. Tutti gli orifizi dei tubi devono essere avvolti con un panno di plastica e impilati il più possibile all'interno in base al numero di sistema. Se le condizioni non lo consentono, deve essere accatastato all'aperto e prestare attenzione a posizionare il cuscino in legno sotto il condotto dell'aria e ci dovrebbero essere misure di protezione affidabili antipioggia, sabbia antivento e protezione solare sopra.
● Pulire il condotto di ventilazione
Il condotto dell'aria deve essere pulito con un detergente neutro che non presenti corrosione sulla superficie del pannello, nessuna polvere dopo l'asciugatura e nessun danno al corpo umano. Innanzitutto, pulire con una soluzione detergente, quindi pulire con acqua pulita e infine pulire la filigrana con un panno bianco pulito. Se non è installato, per il momento, può anche essere asciugato naturalmente, ma dopo l'essiccazione, l'uscita dell'aria deve essere sigillata.
● Mantenere il condotto di ventilazione pulito e in ordine
Il personale addetto all'installazione deve indossare abiti da lavoro, guanti e scarpe da lavoro puliti. Il condotto dell'aria e i suoi componenti che sono stati puliti e sigillati non devono essere smontati prima dell'installazione. Durante l'installazione, rimuovere la pellicola sigillante finale, quindi collegare il connettore; Se c'è una pausa nel mezzo dell'installazione, la porta dovrebbe essere risigillata, in modo da garantire la purificazione dell'impianto di condizionamento.
● Non devono essere posate altre tubazioni nel condotto di ventilazione
La linea elettrica del ventilatore assiale, electric heater, and other equipment installed in the ventilation duct system shall be protected and insulated. The fixed cable of the outdoor riser is strictly prohibited to be pulled on the lightning rod or lightning protection network. When the air duct passes through the wall or floor, it shall not be installed in the wall or floor.
The distance between the air duct and the wall should not be less than 200 mm, and the distance between the air duct and the floor should not be less than 150 mm. When the air duct passes through the fireproof and explosion-proof floor or wall that needs to be closed, the embedded pipe or protective sleeve with the wall thickness of not less than 1.6 mm shall be set, and the flexible material that is non-combustible and harmless to the human body shall be used between the air duct and the protective sleeve.

- L'installazione del condotto di ventilazione deve soddisfare i requisiti di progettazione
The location of the reserved holes in the building structure should be correct, and the holes should be more than 100 mm larger than the outside size of the air duct. The connection interface between the air duct and the air duct of the building structure should be inserted along the airflow direction, and sealing measures should be taken. Flexible short pipe with a length of 150-300 mm shall be set at the joint of the ventilation duct and fan, fan case, air handling machine, etc., or according to the design requirements.
The flexible short pipe should not be used as reducing connecting pipe for alignment and leveling. The length of the flexible short pipe located in the structural deformation joint should be more than 100 mm larger than the width of the deformation joint. The installation slope of the air duct conveying condensate or moisture vapor shall meet the design requirements. It is not suitable to set longitudinal joint at the bottom of air duct, and the joint of air duct should be sealed.
- Collegamento della flangia del condotto di ventilazione
Il materiale della guarnizione deve essere utilizzato al posto di carta spessa, cartone, corda di amianto, fibra di canapa e olio di piombo e carta di linoleum. Il giunto del materiale della guarnizione deve essere ridotto il più possibile. Il giunto del materiale della guarnizione deve essere collegato a forma di trapezio o tenone e deve essere incollato saldamente. La larghezza del materiale della guarnizione dopo che la flangia è stata compressa in modo uniforme deve essere a livello della parete interna del condotto dell'aria. Il giunto tra il condotto dell'aria e la struttura dell'armadio, come il soffitto e la parete divisoria della camera bianca, deve essere a tenuta.
- Il sistema di canali di ventilazione dovrebbe avere buone misure di messa a terra
Quando si passa attraverso la sala di produzione ausiliaria, deve essere a tenuta e non deve essere impostata alcuna interfaccia. Quando la temperatura dell'aria di trasporto è superiore a 80 ℃, devono essere prese misure di protezione per il condotto dell'aria secondo le norme di progettazione. Il foro di misurazione del condotto dell'aria deve essere impostato nella posizione conveniente per la misurazione e l'osservazione; Per il foro di misurazione sul condotto dell'aria nel soffitto, la piastra a soffitto mobile o lo sportello di ispezione devono essere riservati nella posizione corrispondente. Quando si utilizzano flange metalliche e armature metalliche per l'isolamento del condotto dell'aria, devono essere prese misure per prevenire la condensazione del ponte freddo nelle sue parti esposte.
- Il sistema di condotti di ventilazione deve essere controllato per perdite d'aria
Questo è l'ultimo collegamento dell'installazione dell'aria condizionata, ma è il collegamento più importante, quindi il proprietario non deve ignorare questo collegamento nell'accettazione dell'aria condizionata e deve controllare attentamente per evitare perdite d'aria dopo l'installazione del condotto dell'aria .

- Buon senso per la manutenzione dei condotti dell'aria
Dopo l'installazione del condotto di ventilazione, le parti aperte come la bocca del condotto dell'aria e la bocca del filtro che per il momento non sono installate devono essere adeguatamente avvolte con un panno di plastica in tempo per evitare che la polvere penetri nel condotto dell'aria pulita, provocando così un inquinamento secondario nel condotto.
Sono un membro del team di ingegneri per l'installazione dei condotti dell'aria. Sono contento di vedere questo tipo di articolo in anticipo. È ottimo